The garage walls are looking quite good - the cement render has dried, and the gyprock is now installed too.
The slightly moved ditch for the refrigerant lines in case heating and/or cooling is required. The compressor would be located against gyprock wall, about a metre and a half from the back wall. The position is largely dictated by limits of pipe lengths - overall 39m from in-ground manifold to any air cooling unit, likely located in the roof.
The ensuite as seen from the master bedroom, which is mostly missing its gyprock. This was partially remedied by later in the day!
The computer room
and workshop |
Hall on eastern wing,
from garage |
The WC | The ensuite shower |
|
|
Chris adding wood in hall
for gyprock attchment |
|
These are the louvres to be installed in the frame above. They are positioned top to bottom in the above photo, i.e. going away from the camera.