Kitchen Cabinets, Floors and Rain

Click on an image to see a larger version

The Missing Week

Although I called in a couple of times during the week, there was little visible progress and/or I didn't have the camera! Since last week, Sandro has delivered the cabinets for the kitchen, powder room, ensuite, laundry and bathroom. And now the kitchen cabinets are installed (not sure if they are resting there or actually secured). There's been progress with tiling, and the parquet floors have been sanded and the first finish coat applied. And a few more doors, and skirting, and other such stuff. Mostly not highly visible, but important to get things finished.

But the major holdup will be the counter tops. These are Caesarstone, which is a quartz material. Sandro (the cabinet maker) wants the measurements made once all the cabinets are in place. By the time that happens (likely at least a week away) it will be too close to Christmas for delivery this year, which means mid to late January before installation. And thus, of course, no move in before Christmas.

Kitchen

The view from the north west corner of the living room, showing the kicthen cabinets in position, albeit without a counter top. Due to the closeness to Christmas, and the ensuing shutdown, that will not be installed until late January.

The kitchen as seen from the doors from the hall. The refrigerator goes in the cavity on the right, and the microwave and conventional ovens go into the white areas inside the 'tower' on the right, adjacent to the refrigerator location.

The view looking to the north west from where the refrigerator will go. The open area to the right hand end is for the dishwasher. And in the far distance, are the vanities for the bathroom, ensuite, laundry and powder room. These cannot be installed until those areas have tiles on them.

Floors

Since the last batch of photos (a week ago!), the parquet floors have been sanded (yesterday) and this morning had the first finish coat applied. Another 2 will be added tomorrow, and by Monday, all should be ready for use, which in this case means the skirting board can be installed and the painters (arriving Monday) can go to work.

The lounge room floor has been finished completely. The section without grout is today's installation, and hence the gang plank on the lower right to allow access through this area. That was necessary as it was quite rainy, and the garage is the workshop for carpentry.

And this is the toilet. No, that's not the finished floor. But yesterday, Bob the tiler was busy putting cement (I presume, though it's a strange colour) on the wet area floors (ensuite, powder, laundry, toilet) except the bathroom. Although it looks level, it does apparently slope down to the pipe in the middle, which will become the floor drain. Note also that the glass has been placed in the louvre. This was because the bricks were (mostly) washed clean today, and it seemed like it was time to close the louvres to stop the spray coming in. The rain today made no difference to the brick washer, as he gets quite wet anyway. He's coming tomorrow (Saturday) to finish off the area around the garage door.

And the bath is now covered up! Garry was back from holidays this week, so his official brick laying skills were put to good use. And the remaining gyprock has been installed, so it's all go for Bob to come in and finish the floor.

Wet

The western courtyard in the rain. The Vergola is certainly keeping the rain out, as can be seen in the detailed view showing the rain visible against the neighbour's home, and also the rain falling from the guttering's missing downspouts.

As the house is being completed, the workshop area moved to the garage, especially after the floor was poured. Here the crew are putting stuff out of the way of spray from the brick washer tomorrow morning. That's Chris on the left, then Ryan and Garry closest to the camera.


/icons/up.gifBuilding A Home
/icons/right.gifFinishes
/icons/left.gifWET: Wood, Electrical and Tiles