Walking in the gates I noticed some immediate changes. Bricks, and a cement mixer! These are 'common' bricks, used to build the foundations for the slab on the footings, and up to the correct height. They will not be visible when the house is complete.
Garage and switchboard | Dining Room/western courtyard |
This is one of the surveyor's marks. Specifically, the nail in the middle is the spot. The yellow paint highlights the location, as the nails are otherwise not very visible, being a colour close to that of the cement.
The footings are not intended to be well finished, as is shown here on the eastern wall of the kitchen. The left indent was made by the concrete pouring hose.
In a few locations, there are no concrete footings. In this instance, the rock is at the level of the bottom row of bricks, so the bricks will be laid directly onto it. This is the north eastern corner of the lounge room, looking roughly south east.
Lake Como is making its appearance again. This is at the back of bedrooms 1 and 2, and will require proper drainage. You can just see Ryan in the far corner; he and Garry were sorting out the location of the retaining wall along the back fence.
The en-suite is partly over the western sewer line, which is now safely encased in concrete. However, there still must be no load bearing on the pipe, so there are to be two slabs in this area and over the sewer line on the eastern side. The formwork for the lower one is shown here. It will be poured before the main slab, and will be isolated from it with some form of plastic sheet, I believe.
Building A Home
Brickies Ahoy!
The Big Pour I